Road Program
2026 Road Program presentation with Proposed Roads
Preliminary Long-Range Project Schedule
Project Schedule - Updated July 22, 2026
Impacted Resident Notification - Fairway Drive
***July 27, 2026 Updates***
Concrete demo and pour this week : Brookbend Ct, Clarendon Ct, Southridge Cir, then Lily Pond Ln*
Mill & overlay the development between Edgewood Elementary and Silver Lake this week, then Lily Pond Ln*
Proposed schedule is as follows
- 8/10 – Mill S Crescent/Kathryn
- 8/11 – Mill Southridge/Brook, Pave S Crescent/Kathryn
- 8/12 – Mill Clarendon, Pave Southridge/Brook
- 8/13 – Pave Clarendon
*if one day lost due to rain, Lily Pond will be pushed to the remob date, August 10.
**if two days lost due to rain, they will most likely push up our work and stay here while they delay their other commitments.