Road Program

2026 Road Program presentation with Proposed Roads

Preliminary Long-Range Project Schedule

Project Schedule - Updated July 22, 2026

Impacted Resident Notification - Fairway Drive 

***July 27, 2026 Updates***

Concrete demo and pour this week : Brookbend Ct, Clarendon Ct, Southridge Cir, then Lily Pond Ln*

Mill & overlay the development between Edgewood Elementary and Silver Lake this week, then Lily Pond Ln*

 Proposed schedule is as follows

  • 8/10 – Mill S Crescent/Kathryn
  • 8/11 – Mill Southridge/Brook, Pave S Crescent/Kathryn
  • 8/12 – Mill Clarendon, Pave Southridge/Brook
  • 8/13 – Pave Clarendon

 *if one day lost due to rain, Lily Pond will be pushed to the remob date, August 10.

**if two days lost due to rain, they will most likely push up our work and stay here while they delay their other commitments.